Manual Rollback Host Software Deployment
========================================
For a major release software deployment, you can roll back the
For a major release software deployment, you can abort and rollback the
:ref:`manual-host-software-deployment-ee17ec6f71a4` procedure at any time
between :command:`software deploy start` and :command:`software deploy delete`.
After the software deploy deletion step, aborting and rolling back of the major
release deployment is not possible.
.. note::
After the software deploy deletion step, aborting and rolling back of the
major release deployment is not possible.
.. note::
This section also covers the abort and rollback of a new patched major
release deployment.
.. note::
This section describes different rollback procedures based on where you
currently are in the software deployment procedure.
Currently, software deployments cannot be rolled back after the :command:`software
deploy activate` step.
.. contents:: |minitoc|
:local:
:depth: 1
.. rubric:: |prereq|
You are in the middle of the
:ref:`manual-host-software-deployment-ee17ec6f71a4` procedure for a major
release between :command:`software deploy start` and :command:`software deploy
delete`.
Rollback After Successful Software Deploy Activate
--------------------------------------------------
You can roll back the manual host software deployment after a successful
:command:`software deploy activate` in the following scenarios:
- A Patch Release deployment
Immediately after the successful :command:`software deploy activate`
- A major release deployment
- Immediately after the successful :command:`software deploy activate`, before
attempting the Kubernetes upgrade.
- After attempting a Kubernetes upgrade which failed and was rolled back.
.. note::
A rollback of a host major release software deployment can only be done
if Kubernetes has been successfully rolled back to its original
version.
.. _rollbackafterdeployactive:
.. rubric:: |proc|
#. Abort the current in-progress major release software deployment.
#. Verify the current deploy state and Kubernetes current version.
.. code-block::
~(keystone_admin)]$ software deploy abort
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+------------------+
| 24.09.400 | 25.09.0 | True | deploy-completed |
+--------------+------------+------+------------------+
[sysadmin@controller-0 ~(keystone_admin)]$ system kube-version-list
+---------+--------+-----------+
| version | target | state |
+---------+--------+-----------+
| v1.29.2 | True | active |
| v1.30.6 | False | available |
| v1.31.5 | False | available |
| v1.32.2 | False | available |
| v1.33.0 | False | available |
+---------+--------+-----------+
.. _aborthostsoftwaredeploy:
#. Abort the current host software deployment.
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy abort
Deployment has been aborted
#. If the current deploy state is ``deploy-activate-rollback-pending``, then roll back the
activate of the aborted deployment, otherwise proceed to :ref:`3 <manual-rollback-host-software-deployment-9295ce1e6e29-step>`.
#. Verify the deploy state.
.. code-block::
.. code-block:: none
~(keystone_admin)]$ software deploy show
+------------------+------------+------+----------------------------------+
| From Release | To Release | RR | State |
+------------------+------------+------+----------------------------------+
| <new-maj-rel-id> | 10.0.0 | True | deploy-activate-rollback-pending |
+------------------+------------+------+----------------------------------+
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+----------------------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+----------------------------------+
| 25.09.0 | 24.09.400 | True | deploy-activate-rollback-pending |
+--------------+------------+------+----------------------------------+
.. code-block::
#. Perform :command:`deploy activate-rollback` and check the deploy and host deploy states.
~(keystone_admin)]$ software deploy activate-rollback
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy activate-rollback
Deploy activate-rollback has started
When running the :command:`software deploy activate-rollback` command, previous
configurations are applied to the controller.
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+-------------------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+-------------------------------+
| 25.09.0 | 24.09.400 | True | deploy-activate-rollback-done |
+--------------+------------+------+-------------------------------+
Alarm 250.001 (Configuration is out-of-date) is raised and cleared as the
configurations are applied.
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-list
+--------------+--------------+------------+------+------------------------------+
| Host | From Release | To Release | RR | State |
+--------------+--------------+------------+------+------------------------------+
| controller-0 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-pending |
| controller-1 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-pending |
+--------------+--------------+------------+------+------------------------------+
The software deployment state goes from ``activate-rollback-done`` to ``host-rollback``.
.. _rollbackhost:
This may take up to 30 mins to complete depending on system configuration
and hardware.
#. Roll back host.
.. code-block::
Perform the following commands in the order: all worker nodes, all
storage nodes, controller-1, and controller-0:
~(keystone_admin)]$ software deploy show
+------------------+------------+------+---------------+
| From Release | To Release | RR | State |
+------------------+------------+------+---------------+
| <new-maj-rel-id> | 10.0.0 | True | host-rollback |
+------------------+------------+------+---------------+
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ system host-lock <host>
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-rollback <host>
[sysadmin@controller-0 ~(keystone_admin)]$ system host-unlock <host>
.. note::
If :command:`software deploy activate-rollback` fails, that is, if the state is
``activate-rollback-failed``, review ``/var/log/software.log`` on the
active controller for failure details, address the issues, and
re-execute the :command:`software deploy activate-rollback` command.
For controllers, a :command:`system host-swact controller-#` will be
required to lock and roll back the active controller.
#. If the current deploy state is ``host-rollback``, then roll back the
deployment of all the hosts.
.. _verifydeploystate:
.. _manual-rollback-host-software-deployment-9295ce1e6e29-step:
#. Verify the deploy state and host deploy state.
.. code-block::
All the hosts must be in the ``deploy-host-rollback-deployed`` state and the deploy state
should be ``deploy-host-rollback-done``.
~(keystone_admin)]$ software deploy show
+------------------+------------+------+-------------------+
| From Release | To Release | RR | State |
+------------------+------------+------+-------------------+
| <new-maj-rel-id> | 10.0.0 | True | host-rollback |
+------------------+------------+------+-------------------+
.. code-block:: none
If the state is ``host-rollback``, then proceed with the rest of this step,
otherwise proceed to :ref:`4 <manual-rollback-host-software-deployment-9295ce1e6e29-deletestep>`.
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-list
+--------------+--------------+------------+------+-------------------------------+
| Host | From Release | To Release | RR | State |
+--------------+--------------+------------+------+-------------------------------+
| controller-0 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-deployed |
| controller-1 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-deployed |
+--------------+--------------+------------+------+-------------------------------+
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+---------------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+---------------------------+
| 25.09.0 | 24.09.400 | True | deploy-host-rollback-done |
+--------------+------------+------+---------------------------+
- For an |AIO-SX| system
.. _deletecurrentdeploy:
#. Roll back the software release on controller-0.
#. Delete the current deployment.
#. Lock controller-0.
.. code-block:: none
.. code-block::
~(keystone_admin)]$ system host-lock controller-0
#. Roll back the software release on controller-0.
.. code-block::
~(keystone_admin)]$ software deploy host-rollback controller-0
Host installation request sent to controller-0.
Host installation was successful on controller-0
The host is still running the new software release, however boot
parameters have been updated to boot into the previous software
release on the next host reboot, which will occur in the next step
which unlocks the host.
#. Unlock controller-0.
.. code-block::
~(keystone_admin)]$ system host-unlock controller-0
The host will now reboot into the previous software release. Wait for
the host to finish rebooting and become available.
This may take 3-5 mins depending on hardware.
#. Proceed to step :ref:`4
<manual-rollback-host-software-deployment-9295ce1e6e29-deletestep>` of
the main procedure.
- For an |AIO-DX| system or standard system
#. If worker hosts are present, and one or more are in the ``pending-rollback``
state, then roll back the software release on all worker hosts in the
``pending-rollback`` state one at a time. Otherwise, proceed to step :ref:`b <manual-rollback-host-software-deployment-9295ce1e6e29-storagehost>`.
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-pending |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | deploy-host-rollback-deployed|
+--------------+------------------+------------+-------+------------------------------+
#. Roll back the software release on worker-0.
#. Lock worker-0.
.. code-block::
~(keystone_admin)]$ system host-lock worker-0
#. Roll back the software release on worker-0.
.. code-block::
~(keystone_admin)]$ software deploy host-rollback worker-0
Host installation request sent to worker-0
Host installation was successful on worker-0.
The host is still running the new software release, however boot parameters
have been updated to boot into the previous software release on the next
host reboot, which will occur in the next step which unlocks the host.
#. Unlock worker-0.
.. code-block::
~(keystone_admin)]$ system host-unlock worker-0
The host will now reboot into the previous software release. Wait
for the host to finish rebooting and become available. Wait
for all the alarms to clear after the unlock before proceeding to the
next worker host.
This may take 3-5 mins depending on hardware.
#. Display the state of software deployment.
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
+--------------+------------------+------------+-------+------------------+
#. Repeat the above steps for any remaining worker hosts in the ``pending-rollback`` state.
#. If storage hosts are present, and one or more are in the ``pending-rollback`` state,
then roll back the software release on all storage hosts in the ``pending-rollback`` state,
one at a time. Otherwise, proceed to step :ref:`c <manual-rollback-host-software-deployment-9295ce1e6e29-bothcontrollers>`.
.. _manual-rollback-host-software-deployment-9295ce1e6e29-storagehost:
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
+--------------+------------------+------------+-------+------------------+
#. Roll back the software release on storage-0.
#. Lock storage-0.
.. code-block::
~(keystone_admin)]$ system host-lock storage-0
#. Roll back the software release on storage-0.
.. code-block::
~(keystone_admin)]$ software deploy host-rollback storage-0
Host installation request sent to storage-0
Host installation was successful on storage-0.
The host is still running the new software release,
however boot parameters have been updated to boot into
the previous software release on the next host reboot, which
will occur in the next step which unlocks the host.
#. Unlock storage-0.
.. code-block::
~(keystone_admin)]$ system host-unlock storage-0
The host will now reboot into the previous software release. Wait
for the host to finish rebooting and become available. Wait for
all the alarms to clear after the unlock before proceeding to the next
storage host.
This may take 3-5 mins depending on hardware.
#. Display the state of software deployment.
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
+--------------+------------------+------------+-------+------------------+
#. Repeat the above steps for any remaining storage hosts in the
``pending-rollback`` state.
.. note::
After rolling back the first storage host, you can expect alarm
800.003. The alarm is cleared after all the storage hosts are rolled
back.
#. If both the controllers are in the ``pending-rollback`` state, then roll back
controller-0 first.
.. _manual-rollback-host-software-deployment-9295ce1e6e29-bothcontrollers:
#. Ensure that controller-1 is active by switching activity from
controller-0.
.. code-block::
~(keystone_admin)]$ system host-swact controller-0
Wait for the activity to switch to controller-1. This may take up to a
minute depending on hardware. Reconnect to the system.
#. Roll back the software release on controller-0 (the standby controller).
#. Lock controller-0.
.. code-block::
~(keystone_admin)]$ system host-lock controller-0
#. Rollback the software release on controller-0.
.. code-block::
~(keystone_admin)]$ software deploy host-rollback controller-0
Host installation request sent to controller-0.
Host installation was successful on controller-0.
The host is still running the new software release,
however boot parameters have been updated to boot into
the previous software release on the next host reboot, which
will occur in the next step which unlocks the host.
#. Unlock controller-0.
.. code-block::
~(keystone_admin)]$ system host-unlock controller-0
The host will now reboot into the new software release. Wait for
the host to finish rebooting and become available.
This may take 3-5 mins depending on hardware.
#. Display the state of software deployment.
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | pending-rollback |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
+--------------+------------------+------------+-------+------------------+
#. If only controller-1 is in the ``pending-rollback`` state, then roll
back controller-1.
#. Ensure that controller-0 is active by switching activity from
controller-1.
.. code-block::
~(keystone_admin)]$ system host-swact controller-1
Wait for the activity to switch to controller-0.
This may take up to a minute depending on hardware.
Reconnect to the system.
#. Roll back the software release on controller-1 (the standby controller).
#. Lock controller-1
.. code-block::
~(keystone_admin)]$ system host-lock controller-1
#. Roll back the software release on controller-1.
.. code-block::
~(keystone_admin)]$ software deploy host-rollback controller-1
Host installation request sent to controller-1.
Host installation was successful on controller-1.
The host is still running the new software release, however boot
parameters have been updated to boot into the previous software
release on the next host reboot, which will occur in the next step
which unlocks the host.
#. Unlock controller-1.
.. code-block::
~(keystone_admin)]$ system host-unlock controller-1
The host will now reboot into the new software release. Wait for
the host to finish rebooting and become available.
This may take 3-5 mins depending on hardware.
#. Display the state of software deployment.
.. code-block::
~(keystone_admin)]$ software deploy host-list
+--------------+------------------+------------+-------+------------------+
| Host | From Release | To Release | RR | State |
+--------------+------------------+------------+-------+------------------+
| controller-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| controller-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| storage-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-0 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-1 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-2 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
| worker-3 | <new-maj-rel-id> | 10.0.0 | True | rolled back |
+--------------+------------------+------------+-------+------------------+
#. Delete the software deployment to complete the rollback.
.. _manual-rollback-host-software-deployment-9295ce1e6e29-deletestep:
.. code-block::
~(keystone_admin)]$ software deploy delete
Deployment has been deleted
.. code-block::
~(keystone_admin)]$ software deploy show
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy delete
Deploy deleted with success
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
No deploy in progress
#. Confirm that the previous software release is now deployed.
Now, the system is ready for the next host software deployment.
Rollback After Software Deploy Activate Fails
---------------------------------------------
When :command:`software deploy activate` fails, follow the steps below to abort
and roll back the manual host software deployment.
.. rubric:: |proc|
#. Verify current deploy state.
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+------------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+------------------------+
| 24.09.400 | 25.09.0 | True | deploy-activate-failed |
+--------------+------------+------+------------------------+
#. Follow the steps from :ref:`step 2 <aborthostsoftwaredeploy>` to :ref:`step
7 <deletecurrentdeploy>` in :ref:`Rollback After Successful Software Deploy
Activate <rollbackafterdeployactive>`.
Rollback After Software Deploy Host <hostname> Fails
----------------------------------------------------
When deploying software to a host (:command:`software deploy host <hostname>`) fails,
follow the steps below to abort and roll back the manual host software
deployment.
.. rubric:: |proc|
#. Verify the current deploy state.
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy show
+--------------+------------+------+--------------------+
| From Release | To Release | RR | State |
+--------------+------------+------+--------------------+
| 24.09.400 | 25.09.0 | True | deploy-host-failed |
+--------------+------------+------+--------------------+
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-list
+--------------+--------------+------------+------+---------------------+
| Host | From Release | To Release | RR | State |
+--------------+--------------+------------+------+---------------------+
| controller-0 | 25.09.0 | 24.09.400 | True | deploy-host-failed |
| controller-1 | 25.09.0 | 24.09.400 | True | deploy-host-done |
| compute-0 | 25.09.0 | 24.09.400 | True | deploy-host-pending |
+--------------+--------------+------------+------+---------------------+
#. Abort the deploy.
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy abort
Deployment has been aborted
#. Verify the deploy state.
.. code-block:: none
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-list
+--------------+--------------+------------+------+------------------------------+
| Host | From Release | To Release | RR | State |
+--------------+--------------+------------+------+------------------------------+
| controller-0 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-pending |
+--------------+--------------+------------+------+------------------------------+
[sysadmin@controller-0 ~(keystone_admin)]$ software deploy host-list
+--------------+--------------+------------+------+-------------------------------+
| Host | From Release | To Release | RR | State |
+--------------+--------------+------------+------+-------------------------------+
| controller-0 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-pending |
| controller-1 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-pending |
| compute-0 | 25.09.0 | 24.09.400 | True | deploy-host-rollback-deployed |
+--------------+--------------+------------+------+-------------------------------+
Follow :ref:`step 5 <rollbackhost>` in :ref:`Rollback After Successful Software
Deploy Activate <rollbackafterdeployactive>`. Roll back all the hosts that are
in ``deploy-host-rollback-pending`` until all the hosts are in
``deploy-host-rollback-deployed``. Then, follow :ref:`step 6
<verifydeploystate>` and :ref:`step 7 <deletecurrentdeploy>` to complete the
rollback.
Rollback Before Software Deploy Host <hostname> to Any Host
-----------------------------------------------------------
If a host software deployment needs to be cancelled before the software is
deployed to any host, that is, if the deploy state is either
``deploy-start-done`` or ``deploy-start-failed``, you can delete the pending
deployment directly using :command:`software deploy delete`.
.. code-block::
~(keystone_admin)]$ software list
+--------------------------+-------+-----------+
| Release | RR | State |
+--------------------------+-------+-----------+
| starlingx-10.0.0 | True | deployed |
| <new-maj-rel-id> | True | available |
+--------------------------+-------+-----------+