2025 CFN Release Timeline

Event Dates Relative Dates Start Relative Dates Description
Release Start June. 26 Start date Start date Declare Intention: Each sub-project should create or update sub-group introduction and release plan.
Initial Checkpoint July. 10 Start date + 2 weeks Start date + 2 weeks Release plan preparation and review.
Middle Checkpoint Aug. 21 Initial checkpoint + 6 weeks Start date + 8 weeks Progress chack.
Code Freeze Oct. 16 Middle checkpoint + 8 weeks Start date + 16 weeks Cut and lock release branch. Any update of code after this day will NOT be included within current release.
Final Checkpoint Oct. 30 Code freeze + 2 weeks Start date + 18 weeks Each project finish related documentation and release summry for release review.
Formal Release Nov. 13 Final checkpoint + 2 week Start date + 20 weeks Formal release with release tag.