2025 CFN Release Timeline
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | June. 26 | Start date | Start date | Declare Intention: Each sub-project should create or update sub-group introduction and release plan. |
Initial Checkpoint | July. 10 | Start date + 2 weeks | Start date + 2 weeks | Release plan preparation and review. |
Middle Checkpoint | Aug. 21 | Initial checkpoint + 6 weeks | Start date + 8 weeks | Progress chack. |
Code Freeze | Oct. 16 | Middle checkpoint + 8 weeks | Start date + 16 weeks | Cut and lock release branch. Any update of code after this day will NOT be included within current release. |
Final Checkpoint | Oct. 30 | Code freeze + 2 weeks | Start date + 18 weeks | Each project finish related documentation and release summry for release review. |
Formal Release | Nov. 13 | Final checkpoint + 2 week | Start date + 20 weeks | Formal release with release tag. |